Contract for completion of water tower extended by city council

Posted

The Seward City Council on Nov. 3 extended its agreement with Olsson, Inc., for engineering services for the city’s new water tower with plans to complete the attachment of communication equipment on it and begin tearing down the old tower in the spring.

The extension, with a cap on expenditure of $44,500, is the fourth amendment on the Olsson agreement since it was created in 2019 to plan for the water tower. It extends both the timeframe and the scope of services the company will provide.

City Engineer Mike Oneby told the council that Olsson has been able to provide a lot of services within the agreement and this extension will see the project through until it is completed by June 1 and finalized by July 1.

“We have had a lot of issues with the water tower, a lot of unexpected events,” Oneby said.

The work now includes working with the subcontractors installing communication equipment to the tower and climbing the tower to assure communication equipment is properly installed, he said.

In addition, Olsson will coordinate with the city and its demolition contractor for the demolition of the old water tower tank and conduct a completion walkthrough on the new 500,000 gallon water tank and tower.

Olsson will assure project documentation is completed prior to the end of its contract.

Also on Nov. 3, the council approved a lease with T-Mobile Central LLC for installation of that company’s equipment on the tower. The council had recently approved a comparable lease with AT&T and will also have a lease with Verizon.

City Administrator Greg Butcher said the T-Mobile lease reflects that company’s purchase of U.S. Cellular, and customers with U.S. Cellular service should see a difference in their coverage in the area when the equipment is up and running.